| Construction Status

Andromeda, residential wing—
Terrace floor slab cast. Structure complete.
Block masonry in progress on 12th floor.
Internal plastering in progress on 4th floor.

Altair (Serviced Apts) Wing—
16th to terrace floor slab in progress.
Block masonry in progress on 14th floor.
Internal plastering work in progress on 11th floor.

Corona, residential wing—
16th to terrace floor slab in progress.
Block masonry in progress on 16th floor.
Internal plastering completed upto 13th floor.
Plumbing work in progress on 9th floor.

Cygnus, residential wing—
Terrace floor slab completed.
Masonry completed on all floors.
Internal plastering completed upto 17th floor.
Water proofing in progress on 18th floor.
Plumbing work completed.
Tiling work is in progress on 13th floor.
Fire-fighting work completed on all floors.

Leo, residential wing—
Terrace floor slab completed.
Masonry completed on all floors.
Internal plastering completed upto 16th floor.
Plumbing upto 14th floor and water proofing is in progress on 10th floor.
Tiling work in progress on 6th floor.
Fire-fighting work completed upto 13th floor.

Gemini, residential wing—
Terrace floor slab completed.
Masonry completed upto 15th floor.
Internal plastering in progress on 12th and 13th floor.
Plumbing completed upto 9th floor.
Fire-fighting work completed upto 8th floor.

Pegasus, residential wing—
16th floor slab completed.
Block masonry in progress on 7th and 8th floor.
Internal plastering in progress on 2nd floor.
Internal plumbing work in progress on 3rd floors.

Phoenix, residential wing—
16th floor to terrace floor slabs in progress.
Block masonry in progress on 4th and 5th floors.
Internal plastering and plumbing work in progress on 1st to 3rd floors.

Hercules, residential wing—W
13th floor slab completed.
Block masonry in progress on 7th to 9th floors.
Internal plastering and plumbing work in progress.

Polaris, residential wing—
Terrace floor slab and structure completed.
Masonry completed on all floors.
Internal plastering completed upto 17th floor.
Waterproofing completed upto 13th floor.
Plumbing completed upto 14th floor.
Tiling work completed upto 8th floor.
Fire-fighting work completed upto 14th floor.
External plastering work in progress.

Sirius, residential wing—
18th floor slab structure completed.
Masonry and Internal plastering completed upto 16th floor.
Waterproofing completed upto 12th floor.
Internal Plumbing upto 14th floor and tiling completed upto 9th floor.
Fire-fighting work completed upto 13th floor.
External plastering work in progress.

Vega, residential wing—
Terrace floor slab completed.
Masonry completed upto 15th floor.
Internal plastering competed upto 14th floor.
Water proofing completed upto 10th floor.
Plumbing completed upto 11th floor.
Fire-fighting work completed upto 13th floor.

Lynx, residential wing—
Terrace floor slab completed.
Masonry work in progress on 13th floor.
Internal plastering competed upto 11th floor.
Plumbing completed upto 6th floor.
Fire-fighting work completed upto 6th floor.
Club
Ground floor slab in progress
Sheraton Hotel
Basement Level-3 and Level-2 completed.
Ground floor slab nearing completion. First floor slab in progress.
North Star Office tower

23rd floor slab completed. 24th Floor slab in progress.
External structuring work in progress.
Orion Mall

Ground and 1st floor slab completed.
2nd floor nearing completion and 3rd floor slab in progress.
Columbia Asia hospital

Building completed. Has been opened to public.
Multi level car parking
Ground floor completed. Work on 1st to 3rd floors in Progress.
Podium

Podium slab work in progress
|