| Construction Status

Andromeda, residential wing—
The RCC Structure and block masonry is completed.
Plastering is progressing on 12th floor.
Fire fighting piping work is progressing on 4th & 5th floor.

Altair (Serviced Apts) Wing—
RCC Structure and block masonry is completed.
Above terrace floor works is in progress.
Internal plastering is progressing in sixteenth floor.
Internal Fire fighting piping work is progressing on 7th floor.

Corona, residential wing—
Internal plastering is completed up to 17th floor and
progressing on 18th floor.
Toilet tiling and main flooring work is progressing in 9th & 10th floor.
Water proofing work is progressing in 14, 15 & 16th floor.
Internal painting work is in progress.

Cygnus, residential wing—
The masonry, internal plastering, internal plumbing,
water proofing and fire fighting works are fully completed
in all the floors.
Painting work is in progress on 6th floor.
Service lift installation is completed.
Corridor flooring and false ceiling work is progressing in 10th floor.

Leo, residential wing—
The masonry, internal plastering, internal plumbing,
water proofing and fire fighting works are
fully
completed in all the floors.
Internal painting work is progressing in 13th floor.
Tiling work is progressing in 18th floor.
Service lift installation is in progress.
Common corridors, the tiling & the false ceiling work are
progressing on 1st to 5th floor..

Gemini, residential wing—
The masonry, internal plastering, internal plumbing and
fire fighting works are fully completed in all the floors.
Water proofing work is progressing in 16th floor.
Tiling work is progressing in 16th floor.
Internal painting work is progressing in 10th floor.

Pegasus, residential wing—
Structure is completed. The above terrace works is in progress.
Block masonry work is fully completed. Internal plastering work is completed up to 13th floor and progressing in 14th floor.
Internal plumbing work is completed up to 15th floor and
is progressing in 16th floor.
Fire fighting piping work is progressing in 9th floor.
Tiling work is in progress.

Phoenix, residential wing—
Block masonry is completed up to 13th floor and
progressing in 14th to 17th floor.
Internal plastering work is progressing from 9th to 12th floor.
Internal plumbing work is progressing in 9th & 10th floor.
Fire fighting piping work is progressing in 5th & 6th floor.

Hercules, residential wing—
Block masonry work is progressing in 13th to 15th floor.
Fire fighting piping work is progressing in 5th floor.
Internal plumbing work is in progress on 7th & 8th floor.
Internal plastering work is progressing in 9th & 10th floor.
Tiling work is in progress.

Polaris, residential wing—
Internal plumbing work is completed up to 17th floor and
progressing in 18th floor.
Service lift installation is in progress.
False ceiling work is progressing in all the floors
in the corridors and toilets.

Sirius, residential wing—
The Masonry, internal plastering, internal plumbing,
water proofing, fire fighting and tiling work fully
completed at all floors.
Internal painting work is in progress.
False ceiling work is progressing in all the floors in
the corridors and toilets.
Service lift installation work is in progress.

Vega, residential wing—
The masonry, internal plastering, fire fighting work
is fully completed in all the floors.
Internal plumbing work is completed up to 15th floor
and progressing in 16th floor.
Water proofing work is completed up to 15th floor
and progressing in 16th floor.
Tiling work is progressing in 7th floor.

Lynx, residential wing—
Internal plumbing work is completed up to 7th floor.
Tiling work is progressing in 3rd floor.
Water proofing work is completed up to 7th floor.
North Star Office tower

work in progress
Columbia Asia hospital

Open to Public.
Multi level car parking
Work in progress.
|