Status
Photos
as on April 2008

• Finishing works in progress
• External Drain work 100 % completed
• GF (Stilt parking) PCC 100% completed
• Internal Flooring 100% completed
• Door shutters, architrave, Lock fixing 95% completed
• Compound wall 95% completed
• External Road work completed
• Paving work in progress
• Kerb Stone laying in progress
• Lobby texture in progress