| Construction Status Apartments

Acton Block
Structure: Completed
Finishing: Completed
Plastering: Internal completed; External 30% completed

Brixton Block
Structure: Vault roof structure work in progress
Finishing: 1st to 18th floor completed; 19th floor work in progress
Plastering: 1st to 14th compted; 15th & 16th floor work in progress

Coventry Block
Structure: Completed
Finishing: Completed
Plastering: Completed
Flooring: 1st to 18th floor completed; 19th floor work In progress
Painting : In progress

Dartmouth Block
Structure: Completed
Finishing: Completed
Plastering: Completed
Flooring: 17th floor work in progress
Painting: 17th floor work in progress

Earl's Court
Structure: Completed
Finishing: Completed
Plastering: Completed
Flooring: 1st to 15th completed; 16th & 17th floor work In progress
Painting: 18th floor work in progress

Finsbury Block
Structure: Completed
Finishing: Completed
Plastering: Completed
Flooring: 1st to 12th floor completed; 13th & 14th floor work in progress
Painting: 15th & 16th floor work in progress

Greenwich Block
Structure: Completed
Finishing: Completed
Plastering: Internal complted; external 70% completed
Painting: In progress

Hampstead Block
Structure: 10th floor work in progress
Finishing: 1st to 5th floor completed; 6th floor in progress
Plastering: 1st to 3rd floor completed; 4th & 5th floor work in progress

Inverness Block
Structure: Vault roof structure work in progress
Finishing: 1st to 6th floor completed; 7th & 8th floor work in progress

Jackson Block:
Structure: 7th & 8th floor slab work in progress

Kensington Block
Structure: Ground floor slab work in progress

Liverpool Block
Structure: 1st Floor slab work in progress
Summit 1

Structure: Terrace slab completed
Finishing: 1st to 11th floor work in progress
Plastering: 3rd & 4th floor work in progress

Structure: 11th & 12th floor slab work in progress
|