Orion Mall is taking shape on several fronts. Construction is in rapid progress. Some of the main anchor stores have been finalised.
Photos [ as on April 2009 ]

- Third floor slab cast.
- Terrace floor slab progressing in the food-court side.
- Rackers slab for PVR completed.
- Structural steel connecting and central bridge fabrication is in progress.
- PVR side roof truss works are in progress.
- Masonry is progressing on ground, first, second and third floors and PVR auditorium corridors.
- Internal plastering is progressing on first, second and third floors.
- Fire fighting works are progressing on ground, first, second, third floor levels.
- Service tunnel work is in progress.
- STP works in progress.
|