Enquire Now
Enquire Now!
I agree to the Terms & Conditions

Brigade El Dorado

Aerospace Park, Bangalore - Ongoing

RERA STATUS:

Gallium at Brigade El Dorado: PRM/KA/RERA/1251/472/PR/190427/002540.
Helio at Brigade El Dorado: PRM/KA/RERA/1251/472/PR/190913/002889.
Jasper at Brigade El Dorado: PRM/KA/RERA/1250/303/PR/200618/003458
Feldspar at Brigade El Dorado:  

PRM/KA/RERA/1251/309/PR/210216/003909

Krypton at Brigade El Dorado: 

PRM/KA/RERA/1251/309/PR/210518/004158

Iridium at Brigade El Dorado
PRM/KA/RERA/1250/303/PR/200618/003458


Available at https://rera.karnataka.gov.in

Overview

A Brigade home is always one of the wisest investments you can make. A home in North Bangalore, just 15 minutes before the International airport, is nothing short of striking gold. Situated within the Aerospace Park, just minutes away from prominent commercial establishments like Shell Technology Centre, proposed Boeing and Rolls Royce offices, IT Parks and many more, the location is known for its clean wide roads, scenic greenery and impeccable infrastructure.

With Brigade El Dorado, the bar has been further raised, and you are invited to a lifestyle that can well be described as the Gold standard of Community Living!

Other downloads

Master plans / Floor plans

Iridium Masterplan

Download

Krypton Masterplan

Download

Feldspar Masterplan

Download

Gallium Masterplan

Download

Helio Masterplan

Download

Jasper Masterplan

Download

3D Virtual Tour

Status Gallery

Sep 2022 - Helio Block: Wing B - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing B - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing B - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing B - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing C - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing C - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing C - Milestone Release On Commencement of painting 9th to 16th Floor
Sep 2022 - Helio Block: Wing C - Milestone Release On Commencement of painting 9th to 16th Floor
Aug 2022 - Jasper Block: Clubhouse work in progress
Aug 2022 - Jasper Block: Clubhouse work in progress
Aug 2022 - Jasper Block: External Painting
Aug 2022 - Jasper Block: External Painting
Aug 2022 - Jasper Block: Jasper Internal Finishes
Aug 2022 - Jasper Block: Jasper Internal Finishes
Aug 2022 - Jasper Block: Overall Progress
Aug 2022 - Jasper Block: Overall Progress
Aug 2022 - Feldspar Block: Wing C - Structure Work in Progress
Aug 2022 - Feldspar Block: Wing C - Structure Work in Progress
Aug 2022 - Feldspar Block: Wing B - Structure Work in Progress
Aug 2022 - Feldspar Block: Wing B - Structure Work in Progress
Aug 2022 - Feldspar Block: Wing A - Structure Work in Progress
Aug 2022 - Feldspar Block: Wing A - Structure Work in Progress
Aug 2022 - Feldspar Block: Overall Progress
Aug 2022 - Feldspar Block: Overall Progress
Aug 2022 - Gallium Block: MLCP 02
Aug 2022 - Gallium Block: MLCP 02
Aug 2022 - Gallium Block: MLCP 01
Aug 2022 - Gallium Block: MLCP 01
Aug 2022 - Gallium Block: South Elevation
Aug 2022 - Gallium Block: South Elevation
Aug 2022 - Gallium Block: GF to 21st  Floor Elevation - North side
Aug 2022 - Gallium Block: GF to 21st Floor Elevation - North side
Aug 2022 - Helio Block: Podium works
Aug 2022 - Helio Block: Podium works
Aug 2022 - Helio Block: Wing C - Structure and finishing Works in progress
Aug 2022 - Helio Block: Wing C - Structure and finishing Works in progress
Aug 2022 - Helio Block: Wing B
Aug 2022 - Helio Block: Wing B
Aug 2022 - Helio Block: Wing A
Aug 2022 - Helio Block: Wing A
Aug 2022 - Helio Block: South Elevation
Aug 2022 - Helio Block: South Elevation
Aug 2022 - Helio Block: Overall Progress - North Elevation
Aug 2022 - Helio Block: Overall Progress - North Elevation
Aug 2022 - Krypton Block: Basement painting works finishes
Aug 2022 - Krypton Block: Basement painting works finishes
Aug 2022 - Krypton Block: Tiling Works in progress
Aug 2022 - Krypton Block: Tiling Works in progress
Aug 2022 - Krypton Block: Tiling Works in progress
Aug 2022 - Krypton Block: Tiling Works in progress
Aug 2022 - Krypton Block: UGT-Cover Slab Completed
Aug 2022 - Krypton Block: UGT-Cover Slab Completed
Aug 2022 - Krypton Block: Wing B
Aug 2022 - Krypton Block: Wing B
Aug 2022 - Krypton Block: Wing B
Aug 2022 - Krypton Block: Wing B
Aug 2022 - Krypton Block: Wing A
Aug 2022 - Krypton Block: Wing A
Aug 2022 - Krypton Block: Wing A
Aug 2022 - Krypton Block: Wing A
Aug 2022 - Krypton Block: Overall progress
Aug 2022 - Krypton Block: Overall progress
Aug 2022 - Krypton Block: Overall progress
Aug 2022 - Krypton Block: Overall progress
Aug 2022 - Iridium Block: Wings A, B, C - Milestone release on Casting of raft/footing
Aug 2022 - Iridium Block: Wings A, B, C - Milestone release on Casting of raft/footing
Aug 2022 - Feldspar Block: Wing C - Milestone Release on commencement of flooring GF to 8th Floor
Aug 2022 - Feldspar Block: Wing C - Milestone Release on commencement of flooring GF to 8th Floor
Aug 2022 - Feldspar Block: Wing C - Milestone Release on commencement of flooring GF to 8th Floor
Aug 2022 - Feldspar Block: Wing C - Milestone Release on commencement of flooring GF to 8th Floor
Aug 2022 - Feldspar Block: Wing C - Milestone release on Commencement of Fourteenth floor slab
Aug 2022 - Feldspar Block: Wing C - Milestone release on Commencement of Fourteenth floor slab
Aug 2022 - Feldspar Block: Wing B - Milestone release on Commencement of Fourteenth floor slab
Aug 2022 - Feldspar Block: Wing B - Milestone release on Commencement of Fourteenth floor slab
Aug 2022 - Feldspar Block: Wing A - Milestone release on Commencement of tenth floor slab
Aug 2022 - Feldspar Block: Wing A - Milestone release on Commencement of tenth floor slab
Aug 2022 - Krypton Block: Wing A - Milestone Release on commencement of sixteenth floor slab
Aug 2022 - Krypton Block: Wing A - Milestone Release on commencement of sixteenth floor slab
Aug 2022 - Krypton Block: Wing B - Milestone Release on commencement of sixteenth floor slab
Aug 2022 - Krypton Block: Wing B - Milestone Release on commencement of sixteenth floor slab
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Jasper Block: Wing A - Milestone release on commencement of flooring 9th to 16th floor
Aug 2022 - Helio Block: Wing A - Milestone Release  on Commencement of painting 9 to 16th Floor
Aug 2022 - Helio Block: Wing A - Milestone Release on Commencement of painting 9 to 16th Floor
Aug 2022 - Helio Block: Wing B - Milestone Release on Commencement of Doors and Windows
Aug 2022 - Helio Block: Wing B - Milestone Release on Commencement of Doors and Windows
Aug 2022 - Helio Block: Wing C - Milestone Release on Commencement of Doors and Windows
Aug 2022 - Helio Block: Wing C - Milestone Release on Commencement of Doors and Windows
Aug 2022 - Krypton Block: Wing B - Milestone release On commencement of thirteenth floor slab
Aug 2022 - Krypton Block: Wing B - Milestone release On commencement of thirteenth floor slab
Aug 2022 - Krypton Block: Wing A - Milestone release On commencement of thirteenth floor slab
Aug 2022 - Krypton Block: Wing A - Milestone release On commencement of thirteenth floor slab
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of Terrace slab
Aug 2022 - Jasper Block: Wing B - Milestone release on commencement of Terrace slab
1/52

Get In Touch

Similar Projects

apartments in jakkur bangalore
Brigade Bricklane
Brigade Bricklane is a thoughtfully conceived low-rise complex that blends in modern ...
right arrow
View Details
luxury apartments in devanahalli bangalore
Brigade Orchards Luxury Apartments
A ten-minute drive from the airport, these apartments will be built with ...
right arrow
View Details
RERA STATUS:

Gallium at Brigade El Dorado: PRM/KA/RERA/1251/472/PR/190427/002540.
Helio at Brigade El Dorado: PRM/KA/RERA/1251/472/PR/190913/002889.
Jasper at Brigade El Dorado: PRM/KA/RERA/1250/303/PR/200618/003458
Feldspar at Brigade El Dorado:  

PRM/KA/RERA/1251/309/PR/210216/003909

Krypton at Brigade El Dorado: 

PRM/KA/RERA/1251/309/PR/210518/004158

Iridium at Brigade El Dorado
PRM/KA/RERA/1250/303/PR/200618/003458


Available at https://rera.karnataka.gov.in

PRICE:

Gallium and Helio Blocks
2 BHK: 39 Lakhs Onwards*
3 BHK: 48 Lakhs Onwards*
*T & C Apply.

 

Jasper Block:
2 BHK: 40 Lakhs Onwards*
3 BHK: 48 Lakhs Onwards*
*T & C Apply.

 

Feldspar Block
2 BHK: 40 Lakhs Onwards*
3 BHK: 48 Lakhs Onwards*
*T & C Apply.

 

Krypton Block
2 BHK: 40 Lakhs Onwards*
3 BHK: 50 Lakhs Onwards*
*T & C Apply.

 

Iridium Block
1 BHK: 29.99 Lakhs Onwards*
1.5 BHK: 39 Lakhs Onwards*
*T & C Apply.


Offer:

Payment Holiday Till Jan 2024*

TYPE:

2 and 3 Bedroom Homes

SUPER BUILT-UP AREA:

Gallium and Helio Blocks:
74 – 99 Sq.m (795 – 1068 Sq.ft)
Jasper Block:
69 – 145 Sq.m (740 – 1561 Sq.ft)
Feldspar Block:
74 – 99 Sq.m (795 – 1068 Sq.ft)

Krypton Block:
 68.75 - 145.06 Sq.m (795 – 1401 Sq.ft)

Iridium Block
48.40 - 64.07 Sq.m (521 - 690 Sq.ft)

CARPET AREA:

Gallium and Helio Blocks:
43 – 60 Sq.m (466 – 643 Sq.ft)
Jasper Block:
43 – 93 Sq.m (466 – 996 Sq.ft)
Feldspar Block:
43 – 60 Sq.m (463 – 646 Sq.ft)

Krypton Block:
43.32 – 92.58 Sq.m (466– 996 Sq.ft)

Iridium Block
30.40 - 40.29 Sq.m (327 - 434 Sq.ft)

Note: (1 Sq.m = 10.764 Sq.ft)

Features

10-acre Central Park, Swimming Pools, Two Clubhouses, Kid's Play Area, Open-air Amphitheatre, Football Field, Community Gardening, Multipurpose Hall, Creche, Cricket Ground, Convenience Store, Gym
ADDRESS:

Aerospace Park, Near Shell Office,
Huvinayakanahalli, Bengaluru,
Karnataka 562 149.

Social Infrastructure Nearby

Shell Research Centre 3 Kms
SAP 9 Kms
Kempegowda International Airport 11 Kms
Yelahanka 12 Kms
Thanisandra 15 Kms
Budigere Cross 16 Kms
Manyata Tech Park 17 Kms
Hebbal 20 Kms

Share

Similar Projects

apartments in jakkur bangalore
Brigade Bricklane
Brigade Bricklane is a thoughtfully conceived low-rise complex that blends in modern ...
right arrow
View Details
luxury apartments in devanahalli bangalore
Brigade Orchards Luxury Apartments
A ten-minute drive from the airport, these apartments will be built with ...
right arrow
View Details
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Click to call Click To Call