Enquire Now
Enquire Now!
I agree to the Terms & Conditions

Brigade Woods

Whitefield, Bangalore - Ongoing

RERA STATUS:

PRM/KA/RERA/1251/446/PR/180611/001895. Available at www.rera.karnataka.gov.in

Overview

Come Live, Life's Little Treasures. Presenting Brigade Woods, just a handful of woods inspired dream homes that run a gamut of comforts to appeal to both kinds. Home to over 17 different species of flora, Brigade Woods is an exemplary project where nature and modern infrastructure entwine harmoniously. Located in Whitefield, one of the most exciting neighbourhoods in Bangalore, Brigade Woods is next to Brigade Tech Park and is surrounded by IT Parks, hospitals, banks, restaurants and reputed educational institutions. The location is known for its thriving social community and physical infrastructure.

Media

Other downloads

Master plans / Floor plans

Masterplan

Download

Typical Floorplans

Download

Application Form

Allotment Form

Download

3D Virtual Tour

Status Gallery

May 2021 - A Block: Terrace floor grouting and skirting works commenced; South elevation external chajja putty & PHE shaft piping works completed; Window grill installation, Ground floor flats Toilet dado grouting, 1st to 4th floor lobby flooring & railing work-in-progress.
May 2021 - A Block: Terrace floor grouting and skirting works commenced; South elevation external chajja putty & PHE shaft piping works completed; Window grill installation, Ground floor flats Toilet dado grouting, 1st to 4th floor lobby flooring & railing work-in-progress.
May 2021
May 2021
May 2021 - B Block: Terrace flooring, and Up to 4th floor Ledge wall plastering work completed; Staircase railing, Ground floor screed, 4th floor internal wall 1st coat putty work-in-progress.
May 2021 - B Block: Terrace flooring, and Up to 4th floor Ledge wall plastering work completed; Staircase railing, Ground floor screed, 4th floor internal wall 1st coat putty work-in-progress.
May 2021
May 2021
May 2021 - C Block: 4th floor block work commenced; SHR and LMR bottom slab shuttering work-in-progress.
May 2021 - C Block: 4th floor block work commenced; SHR and LMR bottom slab shuttering work-in-progress.
May 2021 - D Block: SHR and LMR bottom shuttering and 4th floor block work-in-progress.
May 2021 - D Block: SHR and LMR bottom shuttering and 4th floor block work-in-progress.
May 2021 - E Block: North & South elevation external painting, and Terrace flooring work-in-progress.
May 2021 - E Block: North & South elevation external painting, and Terrace flooring work-in-progress.
May 2021 - F Block: North & South elevation external painting work-in-progress.
May 2021 - F Block: North & South elevation external painting work-in-progress.
May 2021 - G Block: South elevation balcony railing painting works commenced; UPVC window installation work-in-progress.
May 2021 - G Block: South elevation balcony railing painting works commenced; UPVC window installation work-in-progress.
May 2021 - H Block: Lobby flooring and ceiling primer work commenced.
May 2021 - H Block: Lobby flooring and ceiling primer work commenced.
May 2021 - J Block: 1st to 4th floor lobby flooring, and  UPVC window installation work-in-progress.
May 2021 - J Block: 1st to 4th floor lobby flooring, and UPVC window installation work-in-progress.
May 2021 - K Block: 1st floor wall painting & grouting work, Kitchen utility PHE external shaft piping works commenced;
Ground floor lobby granite cladding, Staircase and lobby area wall putty, and Window grill installation work-in-progress; Main door installation works at 3rd floor.
May 2021 - K Block: 1st floor wall painting & grouting work, Kitchen utility PHE external shaft piping works commenced; Ground floor lobby granite cladding, Staircase and lobby area wall putty, and Window grill installation work-in-progress; Main door installation works at 3rd floor.
May 2021
May 2021
May 2021
May 2021
May 2021 - L Block: Balcony ceiling and wall putty, and UPVC window installation work-in-progre
May 2021 - L Block: Balcony ceiling and wall putty, and UPVC window installation work-in-progre
May 2021 - M Block: Up to 3rd floor 2-coats putty, North elevation external texture, and Up to 3rd floor ledge wall plastering work completed; South elevation pergola works completed and external plastering, 4th floor internal plastering work-in-progress.
May 2021 - M Block: Up to 3rd floor 2-coats putty, North elevation external texture, and Up to 3rd floor ledge wall plastering work completed; South elevation pergola works completed and external plastering, 4th floor internal plastering work-in-progress.
May 2021
May 2021
May 2021 - N Block: North elevation external texture, Up to 3rd floor Lobby plastering, Up to 4th floor ledge wall plastering, South elevation pergola works completed; Terrace floor waterproofing membrane, 4th floor internal plastering work-in-progress; Lift erection/installation works commenced.
May 2021 - N Block: North elevation external texture, Up to 3rd floor Lobby plastering, Up to 4th floor ledge wall plastering, South elevation pergola works completed; Terrace floor waterproofing membrane, 4th floor internal plastering work-in-progress; Lift erection/installation works commenced.
May 2021
May 2021
May 2021
May 2021
May 2021 - P Block: Up to 1st floor 2-coats putty, All toilet high level & wall piping works completed; Internal plastering works - 2nd floor completed and 3rd floor in progress.
May 2021 - P Block: Up to 1st floor 2-coats putty, All toilet high level & wall piping works completed; Internal plastering works - 2nd floor completed and 3rd floor in progress.
May 2021 - Q Block: West elevation external texture, South elevation pergola works completed; Terrace flooring, Lobby railing work-in-progress.
May 2021 - Q Block: West elevation external texture, South elevation pergola works completed; Terrace flooring, Lobby railing work-in-progress.
May 2021
May 2021
May 2021 - R Block: Lift Machine Room plastering, and PHE shaft piping works completed; Terrace flooring,  1st floor flats Toilet dado grouting, Lift installation, and 1st to 4th floor lobby flooring, lift cladding & railing work-in-progress; 1st floor lobby putty works commenced.
May 2021 - R Block: Lift Machine Room plastering, and PHE shaft piping works completed; Terrace flooring, 1st floor flats Toilet dado grouting, Lift installation, and 1st to 4th floor lobby flooring, lift cladding & railing work-in-progress; 1st floor lobby putty works commenced.
May 2021
May 2021
May 2021
May 2021
May 2021 - S Block: North elevation flat-66 series chajja waterproofing & external plastering, and Lift pit waterproofing works completed; North elevation flat-65 series chajja waterproofing, Terrace floor waterproofing testing, North elevation Balcony railing, and LMR internal plastering work-in-progress.
May 2021 - S Block: North elevation flat-66 series chajja waterproofing & external plastering, and Lift pit waterproofing works completed; North elevation flat-65 series chajja waterproofing, Terrace floor waterproofing testing, North elevation Balcony railing, and LMR internal plastering work-in-progress.
May 2021
May 2021
May 2021 - Clubhouse: Reinforcement work-in-progress for connecting slab between club and H block; 2nd floor block work, and Ground floor internal plastering work-in-progress; DG yard painting works, and North elevation external plastering work commenced.
May 2021 - Clubhouse: Reinforcement work-in-progress for connecting slab between club and H block; 2nd floor block work, and Ground floor internal plastering work-in-progress; DG yard painting works, and North elevation external plastering work commenced.
May 2021 - 30
May 2021 - 30
May 2021
May 2021
May 2021 - External development: North side road formation and planter box, Ramp between A and R blocks PCC work-in-progress.
May 2021 - External development: North side road formation and planter box, Ramp between A and R blocks PCC work-in-progress.
May 2021 - 33
May 2021 - 33
May 2021 - 34
May 2021 - 34
1/34

Get In Touch

RERA STATUS:

PRM/KA/RERA/1251/446/PR/180611/001895. Available at www.rera.karnataka.gov.in

PRICE:

Rs. 1.41 Crore onwards*
*Plus Registration.

Offer:
PAYMENT HOLIDAY TILL SEP 2021

 

TYPE:

3 Bedroom apartments

SUPER BUILT-UP AREA:

164 Sq.m

CARPET AREA:

109 Sq.m

Note: (1 Sq.m = 10.764 Sq.ft)

Features

Indoor badminton court, Table tennis room, Multi-purpose hall with pantry space, Snooker room, Indoor kid’s play area, Board & card games area, Terrace party area, Open air theatre, Balinese landscaping, Rainwater harvesting pond, Sandpit area for kids, Multi-purpose open area, Party lawn, Open lawn, Swimming pool, Tennis court, Basketball court, Pavilions with seating, Entrance cascade wall with rock feature
ADDRESS:

Next to Brigade Tech park, Behind GR tech Park, ITPB Main Rd, Pattandur Agrahara, Whitefield, Bengaluru, Karnataka 560066

Share

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Click to call Click To Call