Apr 2024 - Brigade Xanadu Celeste Block P: In progress - External painting in progress & internal QA work in progress
Apr 2024 - Brigade Xanadu Celeste Tower P: In progress - Internal finishing activities. Flat QA in progress (65/112 completed)
Apr 2024 - Brigade Xanadu Celeste Block N: External painting work in progress. Flat QA in progress (08/84 completed)
Apr 2024 - Brigade Xanadu Celeste Block Q: Above terrace structure work, 6th floor Plastering, 1st, 2nd & 3rd floor tiling & painting work, External painting in progress
Apr 2024 - Brigade Xanadu Celeste Block M: Structure –Above Terrace work in progress , 4th , 5th & 6th floor masonry , 2nd & 3rd floor plastering & G floor flooring and painting work in progress
Apr 2024 - Brigade Xanadu Celeste Block R: In progress - Block R –5th & 6th floor slab work, 1st & 2nd floor block work & Ground floor plastering in progress
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Commencement of Painting
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Commencement of Painting
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Commencement of Painting
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Commencement of Painting
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Commencement of Painting
Apr 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Commencement of Fixing of Doors and Windows
Apr 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Commencement of Fixing of Doors and Windows
Apr 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Commencement of Fixing of Doors and Windows
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Casting of 04th Floor Slab
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Casting of 04th Floor Slab
Apr 2024 - Brigade Xanadu Celeste Tower R: Milestone Release On Casting of 04th Floor Slab
Mar 2024 - Brigade Xanadu Celeste Block R: 4
th & 5th floor slab work and 1st & 2nd floor block work in progress
Mar 2024 - Brigade Xanadu Celeste Block M: – Structure –Terrace floor slab pour 01 completed , 4th , 5th & 6th floor masonry , 2nd & 3rd floor plastering & G floor flooring and painting work in progress
Mar 2024 - Brigade Xanadu Celeste Block Q: Above terrace structure work, 6th floor Plastering, 1st & 2nd floor tiling & painting work, External
plastering & painting in progress
Mar 2024 - Brigade Xanadu Celeste Block N: Above terrace works, 5th & 6th floor tiling & painting work in progress
Mar 2024 - Brigade Xanadu Celeste Tower P: Internal finishing activities. Flat QA in progress (42/112 completed)
Mar 2024 - Brigade Xanadu Celeste Block P: External painting in progress & internal QA work in progress
Mar 2024 - Brigade Xanadu Celeste Tower Q: Milestone Release - On Commencement of Fixing of Door and Windows
Mar 2024 - Brigade Xanadu Celeste Tower Q: Milestone Release - On Commencement of Fixing of Door and Windows
Mar 2024 - Brigade Xanadu Celeste Tower M: On commencement of painting
Mar 2024 - Brigade Xanadu Celeste Tower M: On commencement of painting
Mar 2024 - Brigade Xanadu Celeste Tower M: On commencement of painting
Mar 2024 - Brigade Xanadu Celeste Tower M: On commencement of painting
Mar 2024 - Brigade Xanadu Celeste Tower Q: On Commencement of installation of lifts
Mar 2024 - Brigade Xanadu Celeste Tower Q: On Commencement of installation of lifts
Mar 2024 - Brigade Xanadu Celeste Tower N: On Commencement of installation of lifts
Mar 2024 - Brigade Xanadu Celeste Tower N: On Commencement of installation of lifts
Mar 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Casting of 6th Floor Slab
Mar 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Casting of 6th Floor Slab
Mar 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Casting of 6th Floor Slab
Mar 2024 - Brigade Xanadu Celeste Tower M: Milestone Release On Casting of 6th Floor Slab